Pouring a garage slab without the right gravel base is one of the most expensive mistakes in residential concrete work. The gravel distributes load, drains water, and prevents frost heave from cracking the slab in year two. Getting the quantity right the first time saves a second delivery charge and keeps your project on schedule.

Quick-reference table: gravel by garage size

All figures use compactable crusher run at 1.4 tons/cu yd. Cubic yards are pre-compaction (what you order). Ton figures match the order quantity. The 20×20 row is highlighted — the most common two-car size.

Garage Size Sq Ft Cu Yds @ 4″ Cu Yds @ 6″ Tons @ 4″ (+15% comp.)
18 × 20 360 4.4 6.7 7.1
20 × 20 ★ 400 4.9 7.4 7.9
20 × 24 480 5.9 8.9 9.6
24 × 24 576 7.1 10.7 11.5
24 × 30 720 8.9 13.3 14.4

How to read this table: The "Cu Yds @ 4″" column is your raw calculated volume. The "Tons @ 4″" column already includes the 15% compaction factor — that's what you actually order from the supplier. If your supplier quotes only in cubic yards, add 15% to the base volume column yourself.

Have a non-standard size? The calculator handles any dimensions — just enter length, width, and depth.

Use the Calculator →

What type of gravel goes under a garage slab?

Two materials do most of the work, in two separate layers:

#57 crushed stone (optional drainage layer)

This is washed, open-graded stone about 3/4″ in size. It doesn't compact — it stays loose and lets water drain freely. Some builders put 2–3 inches of #57 stone directly under the vapor barrier to create a drainage break between the slab and the soil. It's especially useful on sites with no slope and heavy clay.

Compactable gravel (the main base)

Called crusher run, road base, Class 5, or processed gravel depending on your region. It's a blend of angular crushed stone and stone fines (dust) that locks together under compaction to form a rigid platform. This is what the table above is calculated for. Do not use pea gravel, river rock, or washed round stone as a base. It won't compact and will shift under load.

Never use play sand as a base. It's a common mistake — sand compacts well initially but pumps up through cracks over time in wet conditions. Compactable gravel handles both load-bearing and drainage without this failure mode.

Layer breakdown: what goes where

Concrete slab

4″ minimum for passenger vehicles. 5–6″ for heavy trucks or lifts.

4–6″
6-mil poly vapor barrier

Sits directly on top of the gravel base, under the slab. Prevents ground moisture from wicking up.

—
#57 crushed stone (optional)

Open-graded drainage layer. Use if site has drainage issues or heavy clay. Sits on top of compactable base.

2–3″
Compactable base gravel

Crusher run or road base, compacted in 3-inch lifts. This is the structural layer. This is what you're calculating for.

4–6″
Geotextile fabric

Non-woven 4-oz fabric at the very bottom. Keeps subgrade soil from migrating up into the gravel base over time.

—
Subgrade (native soil)

Must be stripped of topsoil and organics. Slope to drain away from slab center if possible.

—

How deep should gravel be under a garage slab?

4 inches is the minimum for most residential garages on stable, well-draining soil. If the ground freezes in your region and your site drains well, 4 inches is typically sufficient.

6 inches is the right call when:

Some contractors in the far north use 8 inches as a standard. The cost difference between 4 and 6 inches on a 20×20 garage is roughly 2.5 yards — about $100–150 at typical bulk prices. It's cheap insurance.

Step-by-step: measure, calculate, order, spread

  1. 1
    Measure the footprint

    Measure the inside dimensions of the foundation walls, not the outside. If the garage isn't square, break it into rectangles and add the areas.

  2. 2
    Calculate cubic yards

    Formula: (Length × Width × Depth in inches) ÷ 324. For a 20×20 at 4 inches: (20 × 20 × 4) ÷ 324 = 4.94 cubic yards.

  3. 3
    Add 15% for compaction

    Compactable gravel typically loses 10–15% of its volume when compacted. Multiply your cubic yard figure by 1.15. 4.94 × 1.15 = 5.68 yards.

  4. 4
    Convert to tons if needed

    Multiply cubic yards by 1.4 (for crusher run). 5.68 × 1.4 = 7.95 tons. Round up to the nearest half-ton when ordering.

  5. 5
    Order and schedule delivery

    Confirm whether the supplier quotes by the ton or cubic yard. Get delivery 1–2 days before the concrete pour. Wet gravel that sits too long before the pour can shift; fresh is better.

  6. 6
    Spread and compact in lifts

    Spread in 3-inch layers and compact each layer before adding the next. Don't dump all the gravel and compact once — you won't get uniform density at depth.

Worked example: 24×24 garage at 6-inch depth

(24 × 24 × 6) ÷ 324 = 10.67 cu yd raw × 1.15 compaction factor = 12.3 cu yd to order × 1.4 tons/cu yd = 17.2 tons to order

Order 12.5 yards or 17.5 tons. Round up, not down — leftover gravel is useful; coming up short mid-project costs time and a second delivery fee.

Common mistakes when ordering garage base gravel

Save on Materials

Aggregate Markets connects you with local bulk material suppliers for crusher run, road base, and #57 stone. Compare prices from multiple suppliers before you call one.

Compare Local Prices →

Supplies from Home Depot

You'll need a few tools to spread and compact the gravel properly. These are one-time purchases that also get used on driveway and patio projects.

Plate Compactor (rental)

A hand tamper isn't enough for a garage base. Rent a gas plate compactor. Most rental centers stock them for $60–100/day.

Shop at Home Depot →

Landscape / Geotextile Fabric

Use a 4-oz or heavier non-woven geotextile at the base. Avoid thin garden fabric — it tears during gravel placement.

Shop at Home Depot →

6-Mil Poly Sheeting

The vapor barrier goes between the gravel and the slab. Overlap seams by 12 inches and tape them. Pull it up the footings 6 inches on all sides.

Shop at Home Depot →

Steel Wheelbarrow

For moving gravel from the pile to tight spots a loader can't reach. A 6-cu-ft steel tray holds up to 200 lbs. of gravel.

Shop at Home Depot →

Tamping Bar / Hand Tamper

Useful for corners and edges the plate compactor can't reach. Work around the perimeter after every plate compactor pass.

Shop at Home Depot →

Laser Level

Keeps the finished gravel surface flat and at the right elevation before the concrete crew arrives. Rotary laser models project a grade around the whole perimeter.

Shop at Home Depot →

FAQ

A 20×20 garage (400 sq ft) needs approximately 4.9 cubic yards or 6.9 tons of compactable gravel at a 4-inch depth. At 6 inches deep you need 7.4 cubic yards or 10.4 tons. Add 15% for compaction loss, bringing your order to roughly 5.7 yards or 8 tons at 4 inches. See the quick-reference table above for the exact order quantities.

Use compactable gravel — also called crusher run, road base, or Class 5 gravel — as the main base layer. It contains a mix of stone sizes plus stone fines that lock together under compaction. A layer of #57 crushed stone (washed, open-graded) directly under the vapor barrier improves drainage. Never use pea gravel or washed round stone as a base — it won't compact and will shift under load.

4 inches is the minimum for a residential garage slab on stable, well-drained soil. Use 6 inches if the soil has poor drainage, high clay content, or a history of frost heave. Some contractors in cold northern climates use 8 inches as a standard to handle deep freeze lines. The cost difference between 4 and 6 inches on a 20×20 is roughly $100–150 in material — worth it on a new build.

A woven geotextile fabric at the bottom of the gravel base prevents soil from migrating up into the gravel over time — a process called pumping. It's especially important in clay soils. Use a 4-oz or heavier non-woven geotextile, not the thin plastic sheeting sold for weed control. Thin sheeting tears during gravel placement and offers no real benefit.

Compactable gravel (crusher run) typically weighs 1.4 to 1.5 tons per cubic yard. #57 crushed stone runs a bit lighter at 1.3 to 1.4 tons per cubic yard. Use 1.4 as a safe multiplier when your supplier quotes by the ton and you've calculated cubic yards — it's better to order slightly more than to come up short mid-project.